Today we grouted localised voids in walls supported by clay and earth daub reservoirs and gravity grouting larger acres, under pressure from the head achieved by the tank. In both cases the areas were flushed out with water to clean the dirt out of the walls, pre wet the masonry and to ensure that the lime grout would note leak when poured in.
The gravity grouting started at the base of the wall to try and force the grout up and more effectively fill the voids.
In both cases the grout consisted of mature feebly hydraulic lime putty that was beaten to a cream consistency, left to settle over night to allow the excess water to be drained off. Just before use we added a third generation polycaroxylate polymer based superplasticizer
Related Articles

The steps members of the Waterton’s Wall restoration team, with support from Mark Womersley, have been following to consolidate, conserve and repair this historic wall that represents the successful efforts of Charles Waterton to preserve the wildlife that lived on his estate near Wakefield in West Yorkshire.
1. Fill deep voids behind the wall’s facing stones with deep pointing work. The works involve …

Mark spent a day recording a historic timber-framed garden building at Woodsome Hall
Mark Womersley, as part of his voluntary work with the Yorkshire Vernacular Buildings Study Group, spent…

M Womersleys were delighted to offer a day of tutoring to those who attended the Wentworth Woodhouse Working Party
M Womersleys were delighted to offer a day of tutoring to those who attended the Wentworth Woodhouse…